Infrastructure Works, Oban

May 2021- Present

Supply and installation of drainage.

001a
002
003
005
006 ws
007 ws
008 ws
009 ws

Retail Units at Culduthel Mains, Inverness

March 2021- Present

Substructure, drainage and concrete slab with polished finish.

001 Culduthel WS
002 Culduthel WS
003 Culduthel - Concrete Polishing WS
005 Culduthel WS

Urquhart Castle, Gael Force Group 

March 2021

Installation of pathway and concrete block as access to new pontoon facility.

Urquhart Castle 1
Urquhart Castle 2
Urquhart Castle 3
Urquhart Castle 4

Glen Kinglass Hydro, TSL 

February – March 2021

Install and lay over 900m of 500mm DI Pipework.

Glen Kinglass Hydro 1WS
Glen Kinglass Hydro 4WS
Glen Kinglass Hydro 2WS
Glen Kinglass Hydro 3WS

Blar Mhor, TSL – Drainage, Kerblog and Carparks

July 2020 – Present

Continuing work at Blar Mhor housing development.

002 TSL Blar Mhor WS

Blar Mhor, TSL – Deep Drainage

July 2020 – Present

Deep drainage at housing development site in Fort William, dragbox system in place for depths up to 5m.

Blar Mhor 2 WS

COVID-19 

June 2020

We have taken part in some online courses to educate ourselves in taking the proper precautions to ensure the safety of all staff and subcontractors at work.

Training Updates

January 2019 – January 2020

Streetworks Supervisor, Site Management Safety Training Scheme (SMSTS), Distribution Operations Maintenance Strategy (DOMS) and Emergency First Aid at Work are some of the recent updates and current qualifications held by our team.

SMSTS
Emergency First Aid At Work

New House Site, Cannich

June – July 2019

Clear site, foundations, groundshield and services.

Cannich - Access track

Loch Ness Water Treatment Works, Invermoriston – Triple Main With Twin Cable Duct

April – July 2019

Welding, excavation and installation of pipeline along main access road from new WTW to Invermoriston WTW.

LNWTW - Trench

New House Site, Farr

February – March 2019

Foundations and services for a new build.

Farr - Blockworks

Loch Ness Water Treatment Works, Invermoriston – Pipeline

January – April 2019

Installation of 7km of pipeline for Morrisons Construction/ESD.

Retaining Wall, Loch Aline 

May 2018

Hollow block retaining wall and extension under building.

Tullich Water Treatment Works, Oban 

November 2017 – ongoing

Subcontracted to the principal contractor (ESD) to carry out kerbing, drainage and large concrete aprons.  Also, supplying labour and plant to assist ESD to complete the contract.

Temporary Compound for BAM Nuttall, Inverurie

January – March 2018

A job we were able to deliver at short notice subcontracted to Morrisons Construction.  Our role included installing services to a temporary accommodation and welfare units.

Log Cabin Foundations, Aviemore

October – November 2017

Foundations and services to a limited access site.